Healthcare Facility Cuts 43% of HVAC Energy Consumption

A two-story primary care healthcare facility in Miami faced high energy costs and inconsistent HVAC performance, leading to occupant discomfort and business interruptions.
Table of Contents

Challenge

The facility had a Building Management System (BMS), but it was not properly managed and optimized. As a result, the HVAC system operated 24/7 without oversight, causing significant energy waste.

The facility relied on fourteen air conditioning units, five of which were served by a chiller plant with two chilled water pumps.

Solution

  1. Conducted a BAS inspection to assess the initial status of the HVAC control system.
  2. Implemented energy management strategies to eliminate excessive energy waste.

Results

Facility Energy Savings Since 2019

$100,000.00

TOTAL DOLLARS SAVED

The facility achieved an average 43% reduction in overall HVAC power consumption, resulting in over $70,000 in annual energy savings, which have continued since the solutions were implemented in 2019.

Is Your Building’s HVAC System Wasting Energy?

Find out how much you can save with HVAC energy management.

Subscribe to Our Blog
Prevent 90% of Your Facility's Operation Interruptions

Let our team evaluate your smart building infrastructure

More Case Studies